homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

Ved Laurels Phase I

Vednirmitee Projects · P52100045729

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Ved Laurels Phase I (P52100045729), 10 of 158 entries were marked unsold in the MahaRERA home list read 9 September 2026.

MahaRERA · per-home inventory · read 9 September 2026

For Ved Laurels Phase I, ₹8,868 per sq ft of carpet area is the median rate across 93 sold or booked entries with prices in the MahaRERA home list read 9 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 9 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹8,868/ sq ft carpet area

Across 93 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,830 and ₹9,630.

MahaRERA · per-home inventory · read 9 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

158 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 9 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
A Building-Commercial4002290.21–98.10 sq m≈ 971–1,056 sq ft
A Building-Residential281918039.26–39.46 sq m≈ 423–425 sq ft
B Buiilding7236203445.24–104.05 sq m≈ 487–1,120 sq ft
C Building5434101959.74–104.05 sq m≈ 643–1,120 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

158 listed entries

MahaRERA · per-home inventory · read 9 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
Shop No.1A Building-Commercial20598.1 sq m≈ 1,056 sq ftNot for saleNot stated
Shop No.2A Building-Commercial20590.21 sq m≈ 971 sq ftMarked unsoldNot stated
Shop No.3A Building-Commercial20590.39 sq m≈ 973 sq ftNot for saleNot stated
Shop No.4A Building-Commercial20597.73 sq m≈ 1,052 sq ftMarked unsoldNot stated
Ft. No.101A Building-Residential139.26 sq m≈ 423 sq ftSold₹1,617,300
Ft. No.102A Building-Residential139.42 sq m≈ 424 sq ftSold₹1,625,200
Ft. No.103A Building-Residential139.42 sq m≈ 424 sq ftSold₹1,625,200
Ft. No.104A Building-Residential139.46 sq m≈ 425 sq ftSold₹1,636,700
Ft. No.201A Building-Residential239.26 sq m≈ 423 sq ftMarked unsoldNot stated
Ft. No.202A Building-Residential239.42 sq m≈ 424 sq ftSold₹1,625,200
Ft. No.203A Building-Residential239.42 sq m≈ 424 sq ftSold₹1,625,200
Ft. No.204A Building-Residential239.46 sq m≈ 425 sq ftSold₹1,636,700

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹378,733,609 of an estimated ₹512,186,939 was reported as incurred (73.9%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100045729

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
C BuildingExcavation100.0%
C BuildingBasement (if any)100.0%
C BuildingPodiums (if any) 100.0%
C BuildingPlinth100.0%
C BuildingStilt Floor 0.0%
C BuildingSlabs of Super Structure100.0%
C BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
C BuildingSanitary Fittings within the flats / premises100.0%
C BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
C BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
C BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
A Building-ResidentialExcavation100.0%
A Building-ResidentialBasement (if any)100.0%
A Building-ResidentialPodiums (if any) 90.0%
A Building-ResidentialPlinth100.0%
A Building-ResidentialStilt Floor 0.0%
A Building-ResidentialSlabs of Super Structure50.0%
A Building-ResidentialInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15.0%
A Building-ResidentialSanitary Fittings within the flats / premises0.0%
A Building-ResidentialStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45.0%
A Building-ResidentialExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
A Building-ResidentialInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10.0%
A Building-CommercialExcavation100.0%
A Building-CommercialBasement (if any)100.0%
A Building-CommercialPodiums (if any) 50.0%
A Building-CommercialPlinth100.0%
A Building-CommercialStilt Floor 0.0%
A Building-CommercialSlabs of Super Structure20.0%
A Building-CommercialInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5.0%
A Building-CommercialSanitary Fittings within the flats / premises0.0%
A Building-CommercialStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30.0%
A Building-CommercialExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
A Building-CommercialInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
B BuiildingExcavation100.0%
B BuiildingBasement (if any)100.0%
B BuiildingPodiums (if any) 90.0%
B BuiildingPlinth100.0%
B BuiildingStilt Floor 0.0%
B BuiildingSlabs of Super Structure100.0%
B BuiildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90.0%
B BuiildingSanitary Fittings within the flats / premises25.0%
B BuiildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95.0%
B BuiildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50.0%
B BuiildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10.0%

MahaRERA project filing · read 19 July 2026 · registration P52100045729

Reported deadline extensions

Revised targetReason given by the builder
25 September 2027The project site is located adjacent to NH-48 and below a hilly terrain. During the monsoon season, heavy rainfall and slope runoff created difficult and unsafe working conditions, resulting in an unavoidable delay and also we have purchased additional TDR hence time required for approval of the same and extra construction activities due to the same.

MahaRERA project filing · read 19 July 2026 · registration P52100045729

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹75,000,000₹80,000,000₹20,000,000₹175,000,000
Actual raised₹17,641,888₹41,534,558₹370,189,338₹429,365,784

MahaRERA project filing · read 19 July 2026 · registration P52100045729

Quarterly filing record

16 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100045729

Documents named in the filing

  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 3 — CA certificate · 2 listed
  • Form 2 — Engineer's certificate · 2 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 4 listed
  • Sanctioned layout plan · 1 listed
  • Sanctioned building plan · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100045729

Builder and past records

What else does the record show?

Projects registered under this company

Vednirmitee Projects

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold homes

    1. 27 September 2026

      10 marked unsold · 89 sold · 4 booked.

      Saved MahaRERA home list

    2. 18 September 2026

      10 marked unsold · 89 sold · 4 booked.

      Saved MahaRERA home list

    3. 9 September 2026

      10 marked unsold · 89 sold · 4 booked.

      Saved MahaRERA home list

    4. 19 July 2026

      19 marked unsold · 78 sold · 6 booked.

      Saved MahaRERA home list

    These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, home type and price.

    Project Comparison Report

    Which project should you buy in?
    And which home?

    Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-home inventory · read 9 September 2026

    This is a past RERA home list, not current availability. It does not give the date each home was sold.

    Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100045729 ↗
    homeonpaper