The builder’s RERA record, explained

CHAKAN HIGH STREET

CHAKAN BUSINESS HUB LLP · P52100050744

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For CHAKAN HIGH STREET (P52100050744), 50 of 191 entries were marked unsold in the MahaRERA unit list dated 18 July 2026 (saved-file date).

MahaRERA · per-unit inventory · saved-file date 18 July 2026

For CHAKAN HIGH STREET, ₹7,200 per sq ft of filed area is the median rate across 141 sold or booked entries with prices in the MahaRERA unit list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find units to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular unit

See its advantages, drawbacks and how it compares with other units in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended units in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹7,200/ sq ft filed area

Across 141 sold or booked entries with reported prices. The middle 80% of rates fall between ₹4,455 and ₹10,844.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its filed area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold units and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar units sell for?

Compare filed values by building, unit-number pattern and area. See which units were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

191 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and filed areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded filed-area range
BUILDING I191140150013.38–187.76 sq m≈ 144–2,021 sq ft

Area means carpet area for building units and plot area for plots. Size alone does not establish use or layout. How we read and summarise the filing →

Unit Report

Is this the right
unit for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar units and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your unit in the RERA list.

The same unit number may appear in more than one building. Check both before choosing.

191 listed entries

MahaRERA · per-unit inventory · saved-file date 18 July 2026

RERA unit list, not current availability
Unit / buildingFloor in the recordFiled areaReported statusAgreement valueAssess
BLDG I 103BUILDING I / Wing NA120.8101 sq m≈ 224 sq ft · RERA carpet areaSold₹1,120,400
BLDG I 104BUILDING I / Wing NA121.2746 sq m≈ 229 sq ft · RERA carpet areaSold₹1,158,768
BLDG I 105BUILDING I / Wing NA121.832 sq m≈ 235 sq ft · RERA carpet areaSold₹1,712,068
BLDG I 106BUILDING I / Wing NA122.2965 sq m≈ 240 sq ft · RERA carpet areaSold₹1,728,000
BLDG I 107BUILDING I / Wing NA122.7611 sq m≈ 245 sq ft · RERA carpet areaSold₹2,097,776
BLDG I 108BUILDING I / Wing NA124.0617 sq m≈ 259 sq ft · RERA carpet areaMarked unsoldNot stated
BLDG I 109BUILDING I / Wing NA124.5262 sq m≈ 264 sq ft · RERA carpet areaSold₹1,231,000
BLDG I 110BUILDING I / Wing NA125.0836 sq m≈ 270 sq ft · RERA carpet areaSold₹1,909,500
BLDG I 111BUILDING I / Wing NA125.5481 sq m≈ 275 sq ft · RERA carpet areaMarked unsoldNot stated
BLDG I 112BUILDING I / Wing NA126.0126 sq m≈ 280 sq ft · RERA carpet areaMarked unsoldNot stated
BLDG I 113BUILDING I / Wing NA126.57 sq m≈ 286 sq ft · RERA carpet areaMarked unsoldNot stated
BLDG I 114BUILDING I / Wing NA124.8049 sq m≈ 267 sq ft · RERA carpet areaMarked unsoldNot stated

Read every entry in one table: Read the complete saved unit list.

Choose the unit you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹14 of an estimated ₹14 was reported as incurred (95.4%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100050744

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
BUILDING IExcavation100.0%
BUILDING IBasement (if any)100.0%
BUILDING IPodiums (if any) 0.0%
BUILDING IPlinth100.0%
BUILDING IStilt Floor 0.0%
BUILDING ISlabs of Super Structure100.0%
BUILDING IInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65.0%
BUILDING ISanitary Fittings within the flats / premises20.0%
BUILDING IStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40.0%
BUILDING IExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65.0%
BUILDING IInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20.0%

MahaRERA project filing · read 19 July 2026 · registration P52100050744

Reported deadline extensions

Revised targetReason given by the builder
31 December 2026The project has encountered unforeseen challenges that have significantly impacted its timeline and progress. These challenges include: 1. Severe Labor Shortage: o The project has been critically affected by a shortage of skilled labour, which is essential for maintaining the desired quality and pace of construction. o The labour shortage has been exacerbated by external factors, including market-wide labour demand, seasonal migrations, and economic disruptions. This has led to a delay in completing key milestones. 2. Impact on Contractor's Performance: o The labour shortage has directly impacted the contractor's ability to deploy adequate resources, leading to inefficiencies in task execution and prolonged timelines for specific activities. o Furthermore, the reduced availability of skilled workers has resulted in compromises in workmanship quality, necessitating rework and additional supervision to meet the required standards. 3. Ensuring Quality and Compliance: o To deliver the project within the promised quality and safety standards, additional time is essential. Proceeding with limited resources could jeopardize structural integrity and compliance with statutory norms, which is unacceptable for the project and stakeholders. 4. Mitigating Risks and Ensuring Stability: o An extension will provide the project team with the necessary flexibility to resolve workforce constraints, enhance contractor performance, and address inefficiencies without compromising on quality or safety. o This approach aligns with the project's commitment to delivering a robust and sustainable structure while safeguarding the interests of all stakeholders.

MahaRERA project filing · read 19 July 2026 · registration P52100050744

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹84,506,000₹0₹126,759,000₹211,265,000
Actual raised₹81,389,972₹0₹122,084,959₹203,474,931

MahaRERA project filing · read 19 July 2026 · registration P52100050744

Quarterly filing record

13 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100050744

Documents named in the filing

  • Promoter PAN · 1 listed
  • Commencement certificate · 2 listed
  • Occupancy / completion certificate · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 1 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 1 listed
  • Sanctioned building plan · 4 listed
  • Sanctioned layout plan · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100050744

Builder and past records

What else does the record show?

Projects registered under this company

CHAKAN BUSINESS HUB LLP

1Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

    Past records of sales and unsold units

    1. 27 September 2026

      50 marked unsold · 140 sold · 1 booked.

      Saved MahaRERA unit list

    2. 19 September 2026

      50 marked unsold · 140 sold · 1 booked.

      Saved MahaRERA unit list

    3. 10 September 2026

      50 marked unsold · 140 sold · 1 booked.

      Saved MahaRERA unit list

    4. 19 July 2026

      50 marked unsold · 140 sold · 1 booked.

      Saved MahaRERA unit list

    These dates show when the records were saved, not when units were sold. Sales may have changed since then, even if the saved counts are the same.

    More projects to explore

    Other projects in this locality.

    These projects list the same locality. They may differ in exact location, property type and price.

    Project Comparison Report

    Which project should you buy in?
    And which unit?

    Compare up to three projects. We read their plans and RERA documents, recommend units in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

    Create my Comparison Report →

    2 projects · ₹7,999
    3 projects · ₹9,999

    Within 1 working day

    Didn’t help you decide? Full refund — no questions asked.

    Compare project details for free →

    Sources and dates.

    MahaRERA · registration record · read 12 July 2026

    MahaRERA · per-unit inventory · saved-file date 18 July 2026

    This is a past RERA unit list, not current availability. It does not give the date each unit was sold.

    The unit-list date is based on the saved file’s details.

    Filed area means carpet area for building units and plot area for plots. Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

    Open MahaRERA · search P52100050744 ↗