The builder’s RERA record, explained

Godrej Emerald Waters

Godrej Properties Limited · P52100051200

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Godrej Emerald Waters (P52100051200), 357 of 1336 entries were marked unsold in the MahaRERA home list read 19 September 2026.

MahaRERA · per-home inventory · read 19 September 2026

For Godrej Emerald Waters, ₹13,990 per sq ft of carpet area is the median rate across 979 sold or booked entries with prices in the MahaRERA home list read 19 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 19 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹13,990/ sq ft carpet area

Across 979 sold or booked entries with reported prices. The middle 80% of rates fall between ₹12,900 and ₹25,962.

MahaRERA · per-home inventory · read 19 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

1336 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 19 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Commercial Godrej Nexus1161071805.97–157.38 sq m≈ 64–1,694 sq ft
Tower 1 Oceana12354564054.34–140.28 sq m≈ 585–1,510 sq ft
Tower 2 Tropicana12366849054.34–140.28 sq m≈ 585–1,510 sq ft
Tower 3 Lagoon12382041054.34–140.28 sq m≈ 585–1,510 sq ft
Tower 4 Mist123451563054.34–119.77 sq m≈ 585–1,289 sq ft
Tower 5 Coral2421851344042.90–102.30 sq m≈ 462–1,101 sq ft
Tower 6 Wave2421861343042.90–102.30 sq m≈ 462–1,101 sq ft
Tower 7 Aqua244195445046.31–83.91 sq m≈ 498–903 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

1336 listed entries

MahaRERA · per-home inventory · read 19 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
GNRF101Commercial Godrej Nexus162.63 sq m≈ 674 sq ftSold₹19,623,363
GNRF102Commercial Godrej Nexus159.84 sq m≈ 644 sq ftSold₹18,554,028
GNRF103Commercial Godrej Nexus19.97 sq m≈ 107 sq ftSold₹2,993,755
GNRF104Commercial Godrej Nexus19.85 sq m≈ 106 sq ftSold₹2,957,677
GNRF105Commercial Godrej Nexus140.82 sq m≈ 439 sq ftSold₹13,189,547
GNRF106Commercial Godrej Nexus133.29 sq m≈ 358 sq ftSold₹11,604,882
GNRF107Commercial Godrej Nexus132.74 sq m≈ 352 sq ftSold₹10,471,918
GNRF108Commercial Godrej Nexus120.13 sq m≈ 217 sq ftSold₹6,044,418
GNRF109Commercial Godrej Nexus138.72 sq m≈ 417 sq ftSold₹12,767,992
GNRF110Commercial Godrej Nexus138.72 sq m≈ 417 sq ftSold₹12,767,992
GNRF111Commercial Godrej Nexus137.03 sq m≈ 399 sq ftSold₹12,210,846
GNRF112Commercial Godrej Nexus137.03 sq m≈ 399 sq ftSold₹12,210,846

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower 1 OceanaExcavation100.0%
Tower 1 OceanaBasement (if any)100.0%
Tower 1 OceanaPodiums (if any) 100.0%
Tower 1 OceanaPlinth100.0%
Tower 1 OceanaStilt Floor 0.0%
Tower 1 OceanaSlabs of Super Structure29.0%
Tower 1 OceanaInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises6.0%
Tower 1 OceanaSanitary Fittings within the flats / premises0.0%
Tower 1 OceanaStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks6.0%
Tower 1 OceanaExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 1 OceanaInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 2 TropicanaExcavation100.0%
Tower 2 TropicanaBasement (if any)100.0%
Tower 2 TropicanaPodiums (if any) 100.0%
Tower 2 TropicanaPlinth100.0%
Tower 2 TropicanaStilt Floor 0.0%
Tower 2 TropicanaSlabs of Super Structure23.0%
Tower 2 TropicanaInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5.0%
Tower 2 TropicanaSanitary Fittings within the flats / premises0.0%
Tower 2 TropicanaStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks4.0%
Tower 2 TropicanaExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 2 TropicanaInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 3 LagoonExcavation100.0%
Tower 3 LagoonBasement (if any)100.0%
Tower 3 LagoonPodiums (if any) 100.0%
Tower 3 LagoonPlinth100.0%
Tower 3 LagoonStilt Floor 0.0%
Tower 3 LagoonSlabs of Super Structure29.0%
Tower 3 LagoonInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises6.0%
Tower 3 LagoonSanitary Fittings within the flats / premises0.0%
Tower 3 LagoonStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks6.0%
Tower 3 LagoonExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 3 LagoonInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 4 MistExcavation100.0%
Tower 4 MistBasement (if any)100.0%
Tower 4 MistPodiums (if any) 100.0%
Tower 4 MistPlinth100.0%
Tower 4 MistStilt Floor 0.0%
Tower 4 MistSlabs of Super Structure14.0%
Tower 4 MistInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises2.0%
Tower 4 MistSanitary Fittings within the flats / premises0.0%
Tower 4 MistStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2.0%
Tower 4 MistExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 4 MistInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 5 CoralExcavation100.0%
Tower 5 CoralBasement (if any)100.0%
Tower 5 CoralPodiums (if any) 60.0%
Tower 5 CoralPlinth100.0%
Tower 5 CoralStilt Floor 0.0%
Tower 5 CoralSlabs of Super Structure8.0%
Tower 5 CoralInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises1.0%
Tower 5 CoralSanitary Fittings within the flats / premises0.0%
Tower 5 CoralStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks1.0%
Tower 5 CoralExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 5 CoralInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 6 WaveExcavation100.0%
Tower 6 WaveBasement (if any)100.0%
Tower 6 WavePodiums (if any) 100.0%
Tower 6 WavePlinth100.0%
Tower 6 WaveStilt Floor 0.0%
Tower 6 WaveSlabs of Super Structure50.0%
Tower 6 WaveInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10.0%
Tower 6 WaveSanitary Fittings within the flats / premises0.0%
Tower 6 WaveStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10.0%
Tower 6 WaveExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 6 WaveInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 7 AquaExcavation100.0%
Tower 7 AquaBasement (if any)100.0%
Tower 7 AquaPodiums (if any) 100.0%
Tower 7 AquaPlinth100.0%
Tower 7 AquaStilt Floor 0.0%
Tower 7 AquaSlabs of Super Structure31.0%
Tower 7 AquaInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises8.0%
Tower 7 AquaSanitary Fittings within the flats / premises0.0%
Tower 7 AquaStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks7.0%
Tower 7 AquaExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 7 AquaInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Commercial Godrej NexusExcavation100.0%
Commercial Godrej NexusBasement (if any)100.0%
Commercial Godrej NexusPodiums (if any) 0.0%
Commercial Godrej NexusPlinth100.0%
Commercial Godrej NexusStilt Floor 0.0%
Commercial Godrej NexusSlabs of Super Structure100.0%
Commercial Godrej NexusInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Commercial Godrej NexusSanitary Fittings within the flats / premises100.0%
Commercial Godrej NexusStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Commercial Godrej NexusExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Commercial Godrej NexusInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%

MahaRERA project filing · read 19 July 2026 · registration P52100051200

Reported deadline extensions

Revised targetReason given by the builder
28 February 20291. The project involves multiple towers, with 100% excavation completed for Towers T1, T3, T4, T5, T6, T7, and the Commercial Building 2. Plinth work is also fully finished for Towers T5, T6, T7, and for the Commercial Building 3. logistical challenges have delayed excavation for Tower T2, now set to begin in December 2024 4. In light of the upcoming launches of Towers T1 and T2, we seek to amend the registered Agreement and update all future sales documents to reflect the new completion date 5. we seek a change in the project completion date from March 1, 2028, to February 28, 2029 u/s 6 for 1 year only 6. Publishing this revised date would benefit allottees and stakeholders, allowing for informed decisions and fostering transparency. We kindly request the Hon’ble Authority to consider the same

MahaRERA project filing · read 19 July 2026 · registration P52100051200

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹517,488,158₹0₹3,713,677,504₹4,231,165,662
Actual raised₹0₹0₹2,270,066,875₹2,270,066,875

MahaRERA project filing · read 19 July 2026 · registration P52100051200

Quarterly filing record

13 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100051200

Documents named in the filing

  • Occupancy / completion certificate · 3 listed
  • Promoter PAN · 1 listed
  • Commencement certificate · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 5 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 2 listed
  • Sanctioned layout plan · 5 listed
  • Sanctioned building plan · 164 listed
  • Encumbrance certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100051200

Builder and past records

What else does the record show?

Projects registered under this company

Godrej Properties Limited

3Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 27 September 2026

    357 marked unsold · 920 sold · 59 booked.

    Saved MahaRERA home list

  2. 19 September 2026

    357 marked unsold · 920 sold · 59 booked.

    Saved MahaRERA home list

  3. 10 September 2026

    291 marked unsold · 918 sold · 55 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    291 marked unsold · 918 sold · 55 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 19 September 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100051200 ↗