homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

Godrej Elaris

Godrej Properties Limited · PM1260002501385

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Godrej Elaris (PM1260002501385), 618 of 972 entries were marked unsold in the MahaRERA home list read 12 September 2026.

MahaRERA · per-home inventory · read 12 September 2026

For Godrej Elaris, ₹16,481 per sq ft of carpet area is the median rate across 354 sold or booked entries with prices in the MahaRERA home list read 12 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 12 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹16,481/ sq ft carpet area

Across 354 sold or booked entries with reported prices. The middle 80% of rates fall between ₹15,752 and ₹30,100.

MahaRERA · per-home inventory · read 12 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

972 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 12 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Tower A1731229132019.29–214.31 sq m≈ 208–2,307 sq ft
Tower B111381261075.35–122.05 sq m≈ 811–1,314 sq ft
Tower C11101794075.35–99.74 sq m≈ 811–1,074 sq ft
Tower D111481746075.35–122.05 sq m≈ 811–1,314 sq ft
Tower E146602858018.20–165.51 sq m≈ 196–1,782 sq ft
Tower F152662759065.16–200.25 sq m≈ 701–2,155 sq ft
Tower G8400840122.22–149.62 sq m≈ 1,316–1,610 sq ft
Tower H840084085.43–110.61 sq m≈ 920–1,191 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

972 listed entries

MahaRERA · per-home inventory · read 12 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
GEA0101Tower A197.17 sq m≈ 1,046 sq ftMarked unsoldNot stated
GEA0102Tower A175.35 sq m≈ 811 sq ftMarked unsoldNot stated
GEA0103Tower A175.35 sq m≈ 811 sq ftMarked unsoldNot stated
GEA0104Tower A197.17 sq m≈ 1,046 sq ftMarked unsoldNot stated
GEA0201Tower A297.17 sq m≈ 1,046 sq ftMarked unsoldNot stated
GEA0202Tower A275.35 sq m≈ 811 sq ftMarked unsoldNot stated
GEA0203Tower A275.35 sq m≈ 811 sq ftMarked unsoldNot stated
GEA0204Tower A297.17 sq m≈ 1,046 sq ftMarked unsoldNot stated
GEA0301Tower A3122.05 sq m≈ 1,314 sq ftMarked unsoldNot stated
GEA0303Tower A375.35 sq m≈ 811 sq ftMarked unsoldNot stated
GEA0304Tower A397.17 sq m≈ 1,046 sq ftMarked unsoldNot stated
GEA0401Tower A497.17 sq m≈ 1,046 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹4,045,860 of an estimated ₹6,891,574,816 was reported as incurred (0.1%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration PM1260002501385

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower AExcavation0.0%
Tower ABasement (if any)0.0%
Tower APodiums (if any) 0.0%
Tower APlinth0.0%
Tower ASlabs of Super Structure0.0%
Tower AInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower ASanitary Fittings within the flats / premises0.0%
Tower AStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower AExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower AInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower BExcavation0.0%
Tower BBasement (if any)0.0%
Tower BPodiums (if any) 0.0%
Tower BPlinth0.0%
Tower BSlabs of Super Structure0.0%
Tower BInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower BSanitary Fittings within the flats / premises0.0%
Tower BStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower BExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower BInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower CExcavation0.0%
Tower CBasement (if any)0.0%
Tower CPodiums (if any) 0.0%
Tower CPlinth0.0%
Tower CSlabs of Super Structure0.0%
Tower CInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower CSanitary Fittings within the flats / premises0.0%
Tower CStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower CExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower CInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower DExcavation0.0%
Tower DBasement (if any)0.0%
Tower DPodiums (if any) 0.0%
Tower DPlinth0.0%
Tower DSlabs of Super Structure0.0%
Tower DInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower DSanitary Fittings within the flats / premises0.0%
Tower DStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower DExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower DInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower EExcavation0.0%
Tower EBasement (if any)0.0%
Tower EPodiums (if any) 0.0%
Tower EPlinth0.0%
Tower ESlabs of Super Structure0.0%
Tower EInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower ESanitary Fittings within the flats / premises0.0%
Tower EStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower EExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower EInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower FExcavation0.0%
Tower FBasement (if any)0.0%
Tower FPodiums (if any) 0.0%
Tower FPlinth0.0%
Tower FSlabs of Super Structure0.0%
Tower FInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower FSanitary Fittings within the flats / premises0.0%
Tower FStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower FExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower FInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower GExcavation0.0%
Tower GBasement (if any)0.0%
Tower GPodiums (if any) 0.0%
Tower GPlinth0.0%
Tower GSlabs of Super Structure0.0%
Tower GInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower GSanitary Fittings within the flats / premises0.0%
Tower GStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower GExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower GInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower HExcavation0.0%
Tower HBasement (if any)0.0%
Tower HPodiums (if any) 0.0%
Tower HPlinth0.0%
Tower HSlabs of Super Structure0.0%
Tower HInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower HSanitary Fittings within the flats / premises0.0%
Tower HStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower HExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower HInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration PM1260002501385

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹7,022,939,685₹0₹3,968,406,474₹10,991,346,159
Actual raised₹0₹0₹609,614,064₹4,164,571,831

MahaRERA project filing · read 19 July 2026 · registration PM1260002501385

Quarterly filing record

2 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration PM1260002501385

Documents named in the filing

  • Sanctioned building plan · 47 listed
  • Occupancy / completion certificate · 19 listed
  • Commencement certificate · 13 listed
  • Promoter PAN · 3 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned layout plan · 3 listed
  • Title / search report · 1 listed
  • Form 3 — CA certificate · 3 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration PM1260002501385

Builder and past records

What else does the record show?

Projects registered under this company

Godrej Properties Limited

3Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 20 September 2026

    618 marked unsold · 224 sold · 130 booked.

    Saved MahaRERA home list

  2. 12 September 2026

    618 marked unsold · 224 sold · 130 booked.

    Saved MahaRERA home list

  3. 19 July 2026

    698 marked unsold · 169 sold · 105 booked.

    Saved MahaRERA home list

  4. 18 July 2026

    698 marked unsold · 169 sold · 105 booked.

    Saved MahaRERA home list, date based on the saved file

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 12 September 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search PM1260002501385 ↗
homeonpaper