What does the RERA record show?

For ECO GRAM PHASE 3 (P52100052248), 38 of 128 entries were marked unsold in the MahaRERA home list read 19 July 2026.

MahaRERA · per-home inventory · read 19 July 2026

For ECO GRAM PHASE 3, ₹4,628 per sq ft of carpet area is the median rate across 61 sold or booked entries with prices in the MahaRERA home list read 19 July 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 19 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹4,628/ sq ft carpet area

Across 61 sold or booked entries with reported prices. The middle 80% of rates fall between ₹4,021 and ₹5,056.

MahaRERA · per-home inventory · read 19 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

128 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 19 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
B 1161501034.45–43.68 sq m≈ 371–470 sq ft
B 2161600034.45–43.68 sq m≈ 371–470 sq ft
B 3162011334.45–43.68 sq m≈ 371–470 sq ft
B 4160001634.45–43.68 sq m≈ 371–470 sq ft
B 5161402034.45–43.68 sq m≈ 371–470 sq ft
B 6161402034.45–43.68 sq m≈ 371–470 sq ft
B 7160016034.45–43.68 sq m≈ 371–470 sq ft
B 8160016025.94–43.68 sq m≈ 279–470 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

128 listed entries

MahaRERA · per-home inventory · read 19 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
101B 1143.68 sq m≈ 470 sq ftMarked unsoldNot stated
102B 1134.45 sq m≈ 371 sq ftSold₹1,759,208
103B 1134.45 sq m≈ 371 sq ftSold₹1,530,000
104B 1134.45 sq m≈ 371 sq ftSold₹1,875,000
201B 1243.68 sq m≈ 470 sq ftSold₹2,047,222
202B 1234.45 sq m≈ 371 sq ftSold₹1,736,040
203B 1234.45 sq m≈ 371 sq ftSold₹1,898,148
204B 1234.45 sq m≈ 371 sq ftSold₹1,528,050
301B 1343.68 sq m≈ 470 sq ftSold₹2,222,222
302B 1334.45 sq m≈ 371 sq ftSold₹1,899,074
303B 1334.45 sq m≈ 371 sq ftSold₹1,840,000
304B 1334.45 sq m≈ 371 sq ftSold₹1,824,074

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹60,950,872 of an estimated ₹105,592,400 was reported as incurred (57.7%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100052248

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
B 1Excavation100.0%
B 1Basement (if any)0.0%
B 1Podiums (if any) 0.0%
B 1Plinth100.0%
B 1Stilt Floor 0.0%
B 1Slabs of Super Structure100.0%
B 1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
B 1Sanitary Fittings within the flats / premises100.0%
B 1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
B 1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
B 1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
B 2Excavation100.0%
B 2Basement (if any)0.0%
B 2Podiums (if any) 0.0%
B 2Plinth100.0%
B 2Stilt Floor 0.0%
B 2Slabs of Super Structure100.0%
B 2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
B 2Sanitary Fittings within the flats / premises100.0%
B 2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
B 2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
B 2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
B 3Excavation100.0%
B 3Basement (if any)0.0%
B 3Podiums (if any) 0.0%
B 3Plinth100.0%
B 3Stilt Floor 0.0%
B 3Slabs of Super Structure100.0%
B 3Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25.0%
B 3Sanitary Fittings within the flats / premises0.0%
B 3Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
B 3External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
B 3Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
B 4Excavation100.0%
B 4Basement (if any)0.0%
B 4Podiums (if any) 0.0%
B 4Plinth100.0%
B 4Stilt Floor 0.0%
B 4Slabs of Super Structure100.0%
B 4Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25.0%
B 4Sanitary Fittings within the flats / premises0.0%
B 4Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
B 4External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
B 4Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
B 5Excavation100.0%
B 5Basement (if any)0.0%
B 5Podiums (if any) 0.0%
B 5Plinth100.0%
B 5Stilt Floor 0.0%
B 5Slabs of Super Structure100.0%
B 5Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95.0%
B 5Sanitary Fittings within the flats / premises90.0%
B 5Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95.0%
B 5External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95.0%
B 5Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5.0%
B 6Excavation100.0%
B 6Basement (if any)0.0%
B 6Podiums (if any) 0.0%
B 6Plinth100.0%
B 6Stilt Floor 0.0%
B 6Slabs of Super Structure100.0%
B 6Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95.0%
B 6Sanitary Fittings within the flats / premises90.0%
B 6Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95.0%
B 6External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95.0%
B 6Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5.0%
B 7Excavation100.0%
B 7Basement (if any)0.0%
B 7Podiums (if any) 0.0%
B 7Plinth100.0%
B 7Stilt Floor 0.0%
B 7Slabs of Super Structure10.0%
B 7Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
B 7Sanitary Fittings within the flats / premises0.0%
B 7Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
B 7External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
B 7Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
B 8Excavation100.0%
B 8Basement (if any)0.0%
B 8Podiums (if any) 0.0%
B 8Plinth100.0%
B 8Stilt Floor 0.0%
B 8Slabs of Super Structure10.0%
B 8Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
B 8Sanitary Fittings within the flats / premises0.0%
B 8Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
B 8External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
B 8Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100052248

Reported deadline extensions

Revised targetReason given by the builder
31 December 2028The revision involved an increase in the number of wings from B4 to B8, aimed at improving layout efficiency, was received at a later stage owing to delays in obtaining the necessary permissions from the competent authority

MahaRERA project filing · read 19 July 2026 · registration P52100052248

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹30,018,394₹0₹86,784,696₹116,803,090
Actual raised₹0₹0₹76,668,354₹76,668,354

MahaRERA project filing · read 19 July 2026 · registration P52100052248

Quarterly filing record

10 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100052248

Documents named in the filing

  • Occupancy / completion certificate · 2 listed
  • Promoter PAN · 1 listed
  • Commencement certificate · 1 listed
  • Form 1 — Architect's certificate · 5 listed
  • Form 3 — CA certificate · 6 listed
  • Form 2 — Engineer's certificate · 5 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 2 listed
  • Sanctioned building plan · 3 listed
  • Sanctioned layout plan · 2 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100052248

Builder and past records

What else does the record show?

Projects registered under this company

SHRI SIDDHIVINAYAK BUILDERS

5Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 27 September 2026

    38 marked unsold · 61 sold · 0 booked.

    Saved MahaRERA home list

  2. 19 September 2026

    38 marked unsold · 61 sold · 0 booked.

    Saved MahaRERA home list

  3. 10 September 2026

    38 marked unsold · 61 sold · 0 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    38 marked unsold · 61 sold · 0 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 19 July 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100052248 ↗
homeonpaper