Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
PREMIER CITY · P52100078504
For Wisdom Skyverse (P52100078504), 140 of 146 entries were marked unsold in the MahaRERA home list read 11 September 2026.
For Wisdom Skyverse, ₹9,186 per sq ft of carpet area is the median rate across 6 sold or booked entries with prices in the MahaRERA home list read 11 September 2026. These are historical agreement values, not current asking prices.
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹9,186/ sq ft carpet area
Across 6 sold or booked entries with reported prices. The middle 80% of rates fall between ₹7,716 and ₹10,500.
MahaRERA · per-home inventory · read 11 September 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
146 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · read 11 September 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| WING A1 | 106 | 1 | 5 | 100 | 0 | 88.46–112.02 sq m≈ 952–1,206 sq ft |
| WING A2 | 40 | 0 | 0 | 40 | 0 | 88.46–112.02 sq m≈ 952–1,206 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · read 11 September 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| 1001WING A1 | 10 | 112.02 sq m≈ 1,206 sq ft | Marked unsold | Not stated | |
| 1002WING A1 | 10 | 88.46 sq m≈ 952 sq ft | Marked unsold | Not stated | |
| 1003WING A1 | 10 | 88.46 sq m≈ 952 sq ft | Marked unsold | Not stated | |
| 1004WING A1 | 10 | 112.02 sq m≈ 1,206 sq ft | Marked unsold | Not stated | |
| 101WING A1 | 1 | 112.02 sq m≈ 1,206 sq ft | Marked unsold | Not stated | |
| 102WING A1 | 1 | 88.46 sq m≈ 952 sq ft | Marked unsold | Not stated | |
| 103WING A1 | 1 | 88.46 sq m≈ 952 sq ft | Marked unsold | Not stated | |
| 104WING A1 | 1 | 112.02 sq m≈ 1,206 sq ft | Marked unsold | Not stated | |
| 1101WING A1 | 11 | 95.84 sq m≈ 1,032 sq ft | Booked | ₹10,687,386 | |
| 1102WING A1 | 11 | 88.46 sq m≈ 952 sq ft | Marked unsold | Not stated | |
| 1103WING A1 | 11 | 88.46 sq m≈ 952 sq ft | Marked unsold | Not stated | |
| 1104WING A1 | 11 | 112.02 sq m≈ 1,206 sq ft | Marked unsold | Not stated |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹0 of an estimated ₹1,358,251,764 was reported as incurred (0.0%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100078504
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| WING H2 | Excavation | 0.0% |
| WING H2 | Basement (if any) | 0.0% |
| WING H2 | Podiums (if any) | 0.0% |
| WING H2 | Plinth | 0.0% |
| WING H2 | Stilt Floor | 0.0% |
| WING H2 | Slabs of Super Structure | 0.0% |
| WING H2 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| WING H2 | Sanitary Fittings within the flats / premises | 0.0% |
| WING H2 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| WING H2 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| WING H2 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| WING H1 | Excavation | 0.0% |
| WING H1 | Basement (if any) | 0.0% |
| WING H1 | Podiums (if any) | 0.0% |
| WING H1 | Plinth | 0.0% |
| WING H1 | Stilt Floor | 0.0% |
| WING H1 | Slabs of Super Structure | 0.0% |
| WING H1 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| WING H1 | Sanitary Fittings within the flats / premises | 0.0% |
| WING H1 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| WING H1 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| WING H1 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| WING A2 | Excavation | 0.0% |
| WING A2 | Basement (if any) | 0.0% |
| WING A2 | Podiums (if any) | 0.0% |
| WING A2 | Plinth | 0.0% |
| WING A2 | Stilt Floor | 0.0% |
| WING A2 | Slabs of Super Structure | 0.0% |
| WING A2 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| WING A2 | Sanitary Fittings within the flats / premises | 0.0% |
| WING A2 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| WING A2 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| WING A2 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
| WING A1 | Excavation | 0.0% |
| WING A1 | Basement (if any) | 0.0% |
| WING A1 | Podiums (if any) | 0.0% |
| WING A1 | Plinth | 0.0% |
| WING A1 | Stilt Floor | 0.0% |
| WING A1 | Slabs of Super Structure | 0.0% |
| WING A1 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| WING A1 | Sanitary Fittings within the flats / premises | 0.0% |
| WING A1 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| WING A1 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| WING A1 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100078504
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹1,656,460,183 | ₹0 | ₹0 | ₹1,656,460,183 |
| Actual raised | ₹209,057,687 | ₹0 | ₹0 | ₹259,711,651 |
MahaRERA project filing · read 19 July 2026 · registration P52100078504
6 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 19 July 2026 · registration P52100078504
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100078504
Builder and past records
Projects registered under this company
1Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
28 September 2026
140 marked unsold · 1 sold · 5 booked.
Saved MahaRERA home list
20 September 2026
140 marked unsold · 1 sold · 5 booked.
Saved MahaRERA home list
11 September 2026
140 marked unsold · 1 sold · 5 booked.
Saved MahaRERA home list
19 July 2026
146 marked unsold · 0 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Pimpri · Pune
P52100032442
24 of 158 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Pimpri · Pune
P52100051200
357 of 1336 entries marked unsold
MahaRERA · per-home inventory · read 19 September 2026
View project details →Pimpri · Pune
P52100030688
0 of 260 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · read 11 September 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100078504 ↗