The builder’s RERA record, explained

Purva Silversands Phase 2

Pune Projects LLP · P52100005377

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Purva Silversands Phase 2 (P52100005377), 25 of 336 entries were marked unsold in the MahaRERA home list read 4 September 2026.

MahaRERA · per-home inventory · read 4 September 2026

For Purva Silversands Phase 2, ₹8,792 per sq ft of carpet area is the median rate across 311 sold or booked entries with prices in the MahaRERA home list read 4 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 4 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹8,792/ sq ft carpet area

Across 311 sold or booked entries with reported prices. The middle 80% of rates fall between ₹7,293 and ₹9,123.

MahaRERA · per-home inventory · read 4 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

336 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 4 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Phase 2 Building 13362654625022.91–40.80 sq m≈ 247–439 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

336 listed entries

MahaRERA · per-home inventory · read 4 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
PPPLLP-B1-1101Phase 2 Building 11132.38 sq m≈ 349 sq ftSold₹3,019,754
PPPLLP-B1-1102Phase 2 Building 11140.09 sq m≈ 432 sq ftSold₹3,832,050
PPPLLP-B1-1103Phase 2 Building 11139.94 sq m≈ 430 sq ftSold₹3,832,449
PPPLLP-B1-1104Phase 2 Building 11140.14 sq m≈ 432 sq ftBooked₹3,755,118
PPPLLP-B1-1105Phase 2 Building 11140.02 sq m≈ 431 sq ftSold₹3,825,351
PPPLLP-B1-1106Phase 2 Building 11140.02 sq m≈ 431 sq ftSold₹3,876,390
PPPLLP-B1-1107Phase 2 Building 11140.02 sq m≈ 431 sq ftSold₹3,866,484
PPPLLP-B1-1109Phase 2 Building 11127.11 sq m≈ 292 sq ftBooked₹2,582,341
PPPLLP-B1-1110Phase 2 Building 11140.21 sq m≈ 433 sq ftSold₹3,853,639
PPPLLP-B1-1111Phase 2 Building 11140.24 sq m≈ 433 sq ftSold₹3,864,449
PPPLLP-B1-1112Phase 2 Building 11127.11 sq m≈ 292 sq ftBooked₹2,546,449
PPPLLP-B1-1115Phase 2 Building 11130.69 sq m≈ 330 sq ftBooked₹2,924,347

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹387,411,056 of an estimated ₹513,754,946 was reported as incurred (75.4%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 18 July 2026 · registration P52100005377

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Phase 2 Building 1Excavation100.0%
Phase 2 Building 1Basement (if any)100.0%
Phase 2 Building 1Podiums (if any) 100.0%
Phase 2 Building 1Plinth100.0%
Phase 2 Building 1Stilt Floor 100.0%
Phase 2 Building 1Slabs of Super Structure100.0%
Phase 2 Building 1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises78.0%
Phase 2 Building 1Sanitary Fittings within the flats / premises35.0%
Phase 2 Building 1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85.0%
Phase 2 Building 1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.72.0%
Phase 2 Building 1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.78.0%

MahaRERA project filing · read 18 July 2026 · registration P52100005377

Reported deadline extensions

Revised targetReason given by the builder
28 November 2023I state that the completion work of the said project has been delayed due to certain mitigating circumstances. I further state that the promoter of the said project is desirous of completing the balance project completion work at the earliest and has obtained the necessary approvals/sanctions for the same. In view of the facts stated above, I hereby seek an extension of the project registration validity of the said project upto November 28, 2023 under the provisions of section 6 of the Real Estate (Regulation and Development) Act 2016 and the rules and regulations made thereunder.
28 November 2024I state that the completion work of the said project has been delayed due to certain mitigating circumstances. I further state that the promoter of the said project is desirous of completing the balance project completion work at the earliest and has obtained the necessary approvals/sanctions for the same. In view of the facts stated above, I hereby seek an extension of the project registration validity of the said project upto November 28, 2024
28 November 2025We state that the registration validity of the said project has expired on September 30, 2024, and pursuant to the same we have filed an application seeking further extension till Sept 2025 as provided under Section 7 of the act. We hereby wish to state that the building is standalone building in which the 1st ten floors have already been in the stage of completion and the extension is sought only for 11th floor to 21st floor. The delay to achieve completion of the project is neither wilful or deliberate but due to various factors such as fallout of Covid Pandemic, labour exodus, issues with project execution contractors and certain mitigation circumstances. We also wish to state and submit that we have not made any sales for the floors which are above ten floors.
30 October 2026I state that the completion work of the said project has been delayed due to certain mitigating circumstances. I further state that the promoter of the said project is desirous of completing the balance project completion work at the earliest and has obtained the necessary approvals/sanctions for the same. In view of the facts stated above, I hereby seek an extension of the project registration validity of the said project upto 30.10.2025 as we have sought extension only to complete the balance floors that is by 11th to 21st floor we also wish to state and submit that we have obtained OC for 1- 10th Floor.

MahaRERA project filing · read 18 July 2026 · registration P52100005377

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹295,481,626₹0₹0₹295,481,626
Actual raised₹225,459,331₹0₹532,503,285₹757,962,616

MahaRERA project filing · read 18 July 2026 · registration P52100005377

Quarterly filing record

36 elapsed quarterly periods in the captured compliance schedule. Active default was recorded for FY 2025-2026.

MahaRERA project filing · read 18 July 2026 · registration P52100005377

Documents named in the filing

  • Promoter PAN · 1 listed
  • Commencement certificate · 1 listed
  • Form 1 — Architect's certificate · 3 listed
  • Form 3 — CA certificate · 3 listed
  • Form 2 — Engineer's certificate · 3 listed
  • Title / search report · 1 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned layout plan · 3 listed
  • Sanctioned building plan · 1 listed
  • Occupancy / completion certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration P52100005377

Builder and past records

What else does the record show?

Projects registered under this company

Pune Projects LLP

11Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 21 September 2026

    25 marked unsold · 265 sold · 46 booked.

    Saved MahaRERA home list

  2. 13 September 2026

    25 marked unsold · 265 sold · 46 booked.

    Saved MahaRERA home list

  3. 4 September 2026

    25 marked unsold · 265 sold · 46 booked.

    Saved MahaRERA home list

  4. 18 July 2026

    30 marked unsold · 253 sold · 53 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 4 September 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100005377 ↗