The builder’s RERA record, explained

SOLITAIRE BUSINESS HUB PHASE I, SOLITAIRE WORLD

Classic Promoters and Builders Private Limited · P52100017521

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For SOLITAIRE BUSINESS HUB PHASE I, SOLITAIRE WORLD (P52100017521), 116 of 252 entries were marked unsold in the MahaRERA home list read 8 September 2026.

MahaRERA · per-home inventory · read 8 September 2026

For SOLITAIRE BUSINESS HUB PHASE I, SOLITAIRE WORLD, ₹18,083 per sq ft of carpet area is the median rate across 131 sold or booked entries with prices in the MahaRERA home list read 8 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 8 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹18,083/ sq ft carpet area

Across 131 sold or booked entries with reported prices. The middle 80% of rates fall between ₹14,549 and ₹22,274.

MahaRERA · per-home inventory · read 8 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

252 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 8 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
BUILDING 1 - 3rd Floor to 7th Floor2521310116532.14–170.05 sq m≈ 346–1,830 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

252 listed entries

MahaRERA · per-home inventory · read 8 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
OFFICE - 301BUILDING 1 - 3rd Floor to 7th Floor372.45 sq m≈ 780 sq ftMarked unsoldNot stated
OFFICE - 302BUILDING 1 - 3rd Floor to 7th Floor338.97 sq m≈ 419 sq ftMarked unsoldNot stated
OFFICE - 303BUILDING 1 - 3rd Floor to 7th Floor338.97 sq m≈ 419 sq ftMarked unsoldNot stated
OFFICE - 304BUILDING 1 - 3rd Floor to 7th Floor338.97 sq m≈ 419 sq ftMarked unsoldNot stated
OFFICE - 305BUILDING 1 - 3rd Floor to 7th Floor338.97 sq m≈ 419 sq ftMarked unsoldNot stated
OFFICE - 306BUILDING 1 - 3rd Floor to 7th Floor338.97 sq m≈ 419 sq ftMarked unsoldNot stated
OFFICE - 307BUILDING 1 - 3rd Floor to 7th Floor334.74 sq m≈ 374 sq ftMarked unsoldNot stated
OFFICE - 308BUILDING 1 - 3rd Floor to 7th Floor333.45 sq m≈ 360 sq ftMarked unsoldNot stated
OFFICE - 309BUILDING 1 - 3rd Floor to 7th Floor332.14 sq m≈ 346 sq ftMarked unsoldNot stated
OFFICE - 310BUILDING 1 - 3rd Floor to 7th Floor338.97 sq m≈ 419 sq ftMarked unsoldNot stated
OFFICE - 311BUILDING 1 - 3rd Floor to 7th Floor338.97 sq m≈ 419 sq ftMarked unsoldNot stated
OFFICE - 312BUILDING 1 - 3rd Floor to 7th Floor336.49 sq m≈ 393 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹768,401,379 of an estimated ₹969,407,084 was reported as incurred (79.3%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100017521

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
BUILDING 1 - 3rd Floor to 7th FloorExcavation100.0%
BUILDING 1 - 3rd Floor to 7th FloorBasement (if any)100.0%
BUILDING 1 - 3rd Floor to 7th FloorPodiums (if any) 100.0%
BUILDING 1 - 3rd Floor to 7th FloorPlinth0.0%
BUILDING 1 - 3rd Floor to 7th FloorStilt Floor 0.0%
BUILDING 1 - 3rd Floor to 7th FloorSlabs of Super Structure100.0%
BUILDING 1 - 3rd Floor to 7th FloorInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90.0%
BUILDING 1 - 3rd Floor to 7th FloorSanitary Fittings within the flats / premises0.0%
BUILDING 1 - 3rd Floor to 7th FloorStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75.0%
BUILDING 1 - 3rd Floor to 7th FloorExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.67.0%
BUILDING 1 - 3rd Floor to 7th FloorInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.42.0%

MahaRERA project filing · read 19 July 2026 · registration P52100017521

Reported deadline extensions

Revised targetReason given by the builder
29 June 2024due to the covid 19 pandemic, we were not able to construct anymore because of lack of labour contractors and the poor market conditions we were unable to complete the project within the due time.
31 December 2025We are developing a Commercial Project under the name and style “Solitaire Business Hub Phase 1 -Solitaire World” It is stated that the construction and development of the said Project started as per the timelines under RERA. However, the Project got delayed due to the following factors/challenges viz., i. Effect of Covid-19 pandemic, wherein the Government declared nationwide lockdown entire nation suffered a global pandemic i.e., Covid-19 pandemic and various circular orders were passed due to which the construction and development of the said Project stalled, we faced several challenges that adversely affected the construction activities and the project got delayed due to major challenges as stated in Extension application. ii. Further, the appointed contractor/s faced shortage of manpower during Covid-19 pandemic resulting into lack of availability of labor contractors as many of them migrated back to their native places during the lockdown which resulted in shortage of manpower in the market. Due to which reorganizing the labors, restoring the construction and development of the Project took considerable time. Please find attached herewith email reminder sent to contractor to increase the labor at the project. We also faced material shortage during and aftermath of Covid-19 pandemic, which resulted in stalling the project. iii. Thereafter we had to face another challenge in the construction and development activities of the Project i.e., the project got surrounded with the illegal huts having slum encroachments thereby causing obstruction in smooth construction activities. We faced a lot of inconvenience in removing the illegal huts as there was involvement of external elements which were beyond our control that took us considerable time and therefore the project got delayed. A copy of photographs in support thereof is annexed herewith. The work of the project is in process and the RCC work, and Masonry Work is already completed, further the finishing activities are also 72% completed, it will take a further period of 12 Months to complete the overall development of the whole Tower A Commercial building.
31 December 2026As per order of the Hon'ble Chairman (MahaRERA) Dated 02/01/2026. we request you kindly to grant us extension till 31/12/2026.

MahaRERA project filing · read 19 July 2026 · registration P52100017521

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹357,569,500₹142,973,727₹1,457,936,566₹1,958,479,793
Actual raised₹750,491,845₹280,572,010₹702,400,880₹1,733,464,735

MahaRERA project filing · read 19 July 2026 · registration P52100017521

Quarterly filing record

31 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100017521

Documents named in the filing

  • Commencement certificate · 5 listed
  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 4 listed
  • Form 2 — Engineer's certificate · 3 listed
  • Title / search report · 2 listed
  • Form B — Promoter declaration · 2 listed
  • Sanctioned layout plan · 5 listed
  • Sanctioned building plan · 137 listed
  • Occupancy / completion certificate · 2 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100017521

Builder and past records

What else does the record show?

Projects registered under this company

Classic Promoters and Builders Private Limited

15Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 25 September 2026

    116 marked unsold · 131 sold · 0 booked.

    Saved MahaRERA home list

  2. 17 September 2026

    116 marked unsold · 131 sold · 0 booked.

    Saved MahaRERA home list

  3. 8 September 2026

    116 marked unsold · 131 sold · 0 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    116 marked unsold · 131 sold · 0 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 8 September 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100017521 ↗