Buyer’s Report
Understand this project
Find homes to consider, with advice on light, layout, privacy and surroundings.
₹4,999
Builder’s RERA records,
explained for buyers.
The builder’s RERA record, explained
Classic Promoters and Builders Private Limited · P52100017591
For SOLITAIRE BUSINESS HUB PHASE II, SOLITAIRE WORLD (P52100017591), 183 of 236 entries were marked unsold in the MahaRERA home list read 8 September 2026.
For SOLITAIRE BUSINESS HUB PHASE II, SOLITAIRE WORLD, ₹15,310 per sq ft of carpet area is the median rate across 53 sold or booked entries with prices in the MahaRERA home list read 8 September 2026. These are historical agreement values, not current asking prices.
These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.
Builder’s completion target
The builder reported this target date. It is not a confirmed handover date.
Status shown on RERA
This is the status shown on RERA. It does not confirm an occupancy certificate or today’s construction progress.
Prices reported to RERA
₹15,310/ sq ft carpet area
Across 53 sold or booked entries with reported prices. The middle 80% of rates fall between ₹13,509 and ₹16,437.
MahaRERA · per-home inventory · read 8 September 2026
For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.
Sales Report
Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.
Inside this registered phase
236 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.
MahaRERA · per-home inventory · read 8 September 2026
Scroll sideways to see all columns.
| Filed building | Entries | Sold | Booked | Marked unsold | Other / unstated status | Recorded carpet-area range |
|---|---|---|---|---|---|---|
| Building 1 - 8th to 15th Floor | 92 | 15 | 0 | 77 | 0 | 33.54–1,123.28 sq m≈ 361–12,091 sq ft |
| Building 2 - 16th Floor | 15 | 4 | 0 | 11 | 0 | 39.67–143.26 sq m≈ 427–1,542 sq ft |
| Building 3 - 17th Floor to 25th Floor | 110 | 29 | 0 | 81 | 0 | 39.67–764.42 sq m≈ 427–8,228 sq ft |
| Building 4 - 26th Floor to 28th Floor | 19 | 5 | 0 | 14 | 0 | 39.80–432.11 sq m≈ 428–4,651 sq ft |
Different sizes are not necessarily different bedroom types. How we read and summarise the filing →
Unit Report
Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.
Didn’t help you decide? Full refund — no questions asked.
The same home number may appear in more than one building. Check both before choosing.
MahaRERA · per-home inventory · read 8 September 2026
| Home / building | Floor in the record | Carpet area | Reported status | Agreement value | Assess |
|---|---|---|---|---|---|
| OFFICE - 1001Building 1 - 8th to 15th Floor | 10 | 1123.28 sq m≈ 12,091 sq ft | Marked unsold | Not stated | |
| OFFICE - 1101Building 1 - 8th to 15th Floor | 11 | 86.31 sq m≈ 929 sq ft | Marked unsold | Not stated | |
| OFFICE - 1102, 1103Building 1 - 8th to 15th Floor | 11 | 86.12 sq m≈ 927 sq ft | Sold | ₹14,976,914 | |
| OFFICE - 1104Building 1 - 8th to 15th Floor | 11 | 42.83 sq m≈ 461 sq ft | Marked unsold | Not stated | |
| OFFICE - 1105Building 1 - 8th to 15th Floor | 11 | 42.83 sq m≈ 461 sq ft | Marked unsold | Not stated | |
| OFFICE - 1106Building 1 - 8th to 15th Floor | 11 | 110.93 sq m≈ 1,194 sq ft | Marked unsold | Not stated | |
| OFFICE - 1107Building 1 - 8th to 15th Floor | 11 | 39.67 sq m≈ 427 sq ft | Sold | ₹5,014,572 | |
| OFFICE - 1108Building 1 - 8th to 15th Floor | 11 | 42.83 sq m≈ 461 sq ft | Marked unsold | Not stated | |
| OFFICE - 1109Building 1 - 8th to 15th Floor | 11 | 42.83 sq m≈ 461 sq ft | Sold | ₹7,217,000 | |
| OFFICE - 1110Building 1 - 8th to 15th Floor | 11 | 42.83 sq m≈ 461 sq ft | Marked unsold | Not stated | |
| OFFICE - 1111Building 1 - 8th to 15th Floor | 11 | 42.83 sq m≈ 461 sq ft | Marked unsold | Not stated | |
| OFFICE - 1112, 1112ABuilding 1 - 8th to 15th Floor | 11 | 86.12 sq m≈ 927 sq ft | Sold | ₹14,868,113 |
Read every entry in one table: Read the complete saved home list.
Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.
More from the RERA documents
₹1,059,766,006 of an estimated ₹1,536,977,437 was reported as incurred (69.0%). This percentage is about costs. It does not show how much construction is complete.
MahaRERA project filing · read 19 July 2026 · registration P52100017591
Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.
| Building | Activity | Reported |
|---|---|---|
| Building 1 - 8th to 15th Floor | Excavation | 100.0% |
| Building 1 - 8th to 15th Floor | Basement (if any) | 100.0% |
| Building 1 - 8th to 15th Floor | Podiums (if any) | 100.0% |
| Building 1 - 8th to 15th Floor | Plinth | 0.0% |
| Building 1 - 8th to 15th Floor | Stilt Floor | 100.0% |
| Building 1 - 8th to 15th Floor | Slabs of Super Structure | 100.0% |
| Building 1 - 8th to 15th Floor | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 73.0% |
| Building 1 - 8th to 15th Floor | Sanitary Fittings within the flats / premises | 0.0% |
| Building 1 - 8th to 15th Floor | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 72.0% |
| Building 1 - 8th to 15th Floor | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 68.0% |
| Building 1 - 8th to 15th Floor | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 44.0% |
| Building 2 - 16th Floor | Excavation | 100.0% |
| Building 2 - 16th Floor | Basement (if any) | 100.0% |
| Building 2 - 16th Floor | Podiums (if any) | 100.0% |
| Building 2 - 16th Floor | Plinth | 0.0% |
| Building 2 - 16th Floor | Stilt Floor | 100.0% |
| Building 2 - 16th Floor | Slabs of Super Structure | 100.0% |
| Building 2 - 16th Floor | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 67.0% |
| Building 2 - 16th Floor | Sanitary Fittings within the flats / premises | 0.0% |
| Building 2 - 16th Floor | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 72.0% |
| Building 2 - 16th Floor | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 57.0% |
| Building 2 - 16th Floor | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 44.0% |
| Building 3 - 17th Floor to 25th Floor | Excavation | 100.0% |
| Building 3 - 17th Floor to 25th Floor | Basement (if any) | 100.0% |
| Building 3 - 17th Floor to 25th Floor | Podiums (if any) | 100.0% |
| Building 3 - 17th Floor to 25th Floor | Plinth | 0.0% |
| Building 3 - 17th Floor to 25th Floor | Stilt Floor | 100.0% |
| Building 3 - 17th Floor to 25th Floor | Slabs of Super Structure | 100.0% |
| Building 3 - 17th Floor to 25th Floor | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 52.0% |
| Building 3 - 17th Floor to 25th Floor | Sanitary Fittings within the flats / premises | 0.0% |
| Building 3 - 17th Floor to 25th Floor | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 71.0% |
| Building 3 - 17th Floor to 25th Floor | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 42.0% |
| Building 3 - 17th Floor to 25th Floor | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 44.0% |
| Building 4 - 26th Floor to 28th Floor | Excavation | 100.0% |
| Building 4 - 26th Floor to 28th Floor | Basement (if any) | 100.0% |
| Building 4 - 26th Floor to 28th Floor | Podiums (if any) | 100.0% |
| Building 4 - 26th Floor to 28th Floor | Plinth | 0.0% |
| Building 4 - 26th Floor to 28th Floor | Stilt Floor | 100.0% |
| Building 4 - 26th Floor to 28th Floor | Slabs of Super Structure | 100.0% |
| Building 4 - 26th Floor to 28th Floor | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 37.0% |
| Building 4 - 26th Floor to 28th Floor | Sanitary Fittings within the flats / premises | 0.0% |
| Building 4 - 26th Floor to 28th Floor | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 65.0% |
| Building 4 - 26th Floor to 28th Floor | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 29.0% |
| Building 4 - 26th Floor to 28th Floor | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 44.0% |
| Building 5 | Excavation | 0.0% |
| Building 5 | Basement (if any) | 0.0% |
| Building 5 | Podiums (if any) | 0.0% |
| Building 5 | Plinth | 0.0% |
| Building 5 | Stilt Floor | 0.0% |
| Building 5 | Slabs of Super Structure | 0.0% |
| Building 5 | Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0.0% |
| Building 5 | Sanitary Fittings within the flats / premises | 0.0% |
| Building 5 | Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0.0% |
| Building 5 | External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0.0% |
| Building 5 | Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0.0% |
MahaRERA project filing · read 19 July 2026 · registration P52100017591
| Revised target | Reason given by the builder |
|---|---|
| 30 September 2025 | due to the covid 19 pandemic, we were not able to construct anymore because of lack of labour contractors and the poor market conditions we were unable to complete the project within the due time. |
| 31 March 2027 | As per order of the Hon'ble Chairman (MahaRERA) Dated 14/11/2025 we request you kindly to grant us extension till 31/03/2027 We submit this application for extension of project registration in accordance with MahaRERA Order No. 40/2022. dated 27/12/2022 seeking extension of the project registration. The necessary documents have been uploaded as per the requirement. Below is a summary of the documents submitted As on date, the project stands at 65% completion. Despite multiple challenges, we have maintained consistent efforts to ensure project execution. Documents Uploaded accordingly 1.Format B uploaded in tab 1 2.Revised form B uploaded in Tab 2 3.Form E Uploaded in tab 3 4.The Reasons in details why the required percentage of consents from the allotees could not be obtained as well as list the efforts taken by them for obtaining same – Uploaded in tab 4 5.The Reason why the application of extension should be considered without the required 51% consent from allottees- Uploaded in tab 5 6.An explanatory note setting out the grounds and reason for delay in completion of the real estate project, the need for grant of extension along with supporting documents- Uploaded in other tab 6 7.Shall Provide the list of complaints filed before MahaRERA or Before any court Law, Tribunal, Forums, NCLT along with details and passed their- Uploaded in tab 7 8.Notarised Declaration as per Order No. 40- Uploaded in tab 8 9.PERT Chart- uploaded in Tab 9 •Illegal slum encroachments around the project layout hindered site access and progress. •Official correspondence was made with PMC and Police seeking assistance for clearance. Enclosed supporting documents: 10.Sr. Police Inspector’s letter to PMC dated 26.01.2024 in tab 10 11.PMC’s letter dated to Sr police inspector 28.01.2024 in tab 11 12.slum clearance report dated 31 Jan 2024 in Tab 12 13.Damage due to slum dweller-uploaded in Tab 13 14.Press Note dated 03.08.2024Heavy Vehicle Restriction uploaded in Tab 14 15.Press Note dated 30.06.2025Heavy Vehicle Restriction uploaded in Tab 1o |
MahaRERA project filing · read 19 July 2026 · registration P52100017591
RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.
| Filing | Own funds | Borrowing | Payments from buyers | Total |
|---|---|---|---|---|
| Estimated plan | ₹952,191,385 | ₹599,935,231 | ₹531,490,514 | ₹2,083,617,131 |
| Actual raised | ₹1,063,298,669 | ₹396,839,072 | ₹489,311,578 | ₹1,949,449,318 |
MahaRERA project filing · read 19 July 2026 · registration P52100017591
31 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.
MahaRERA project filing · read 19 July 2026 · registration P52100017591
A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.
MahaRERA project filing · read 19 July 2026 · registration P52100017591
Builder and past records
Projects registered under this company
15Pune registrations
These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.
MahaRERA Pune registration records · read 12 July 2026
Past records of sales and unsold homes
25 September 2026
183 marked unsold · 53 sold · 0 booked.
Saved MahaRERA home list
17 September 2026
183 marked unsold · 53 sold · 0 booked.
Saved MahaRERA home list
8 September 2026
183 marked unsold · 53 sold · 0 booked.
Saved MahaRERA home list
19 July 2026
183 marked unsold · 53 sold · 0 booked.
Saved MahaRERA home list
These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.
More projects to explore
These projects list the same locality. They may differ in exact location, home type and price.
Bibwewadi · Pune
P52100050511
25 of 127 entries marked unsold
MahaRERA · per-home inventory · saved-file date 18 July 2026
View project details →Bibwewadi · Pune
P52100022645
561 of 1317 entries marked unsold
MahaRERA · per-home inventory · read 8 September 2026
View project details →Bibwewadi · Pune
P52100078873
150 of 256 entries marked unsold
MahaRERA · per-home inventory · read 11 September 2026
View project details →Project Comparison Report
Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.
2 projects · ₹7,999
3 projects · ₹9,999
Within 1 working day
Didn’t help you decide? Full refund — no questions asked.
Compare project details for free →MahaRERA · registration record · read 12 July 2026
MahaRERA · per-home inventory · read 8 September 2026
This is a past RERA home list, not current availability. It does not give the date each home was sold.
Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.
Open MahaRERA · search P52100017591 ↗