homeonpaper.

Builder’s RERA records,
explained for buyers.

The builder’s RERA record, explained

GODREJ BOULEVARD

Manjari Housing Projects LLP · P52100024616

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For GODREJ BOULEVARD (P52100024616), 10 of 780 entries were marked unsold in the MahaRERA unit list dated 18 July 2026 (saved-file date).

MahaRERA · per-unit inventory · saved-file date 18 July 2026

For GODREJ BOULEVARD, ₹9,254 per sq ft of filed area is the median rate across 770 sold or booked entries with prices in the MahaRERA unit list dated 18 July 2026 (saved-file date). These are historical agreement values, not current asking prices.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find units to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular unit

See its advantages, drawbacks and how it compares with other units in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended units in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹9,254/ sq ft filed area

Across 770 sold or booked entries with reported prices. The middle 80% of rates fall between ₹8,538 and ₹10,877.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its filed area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold units and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar units sell for?

Compare filed values by building, unit-number pattern and area. See which units were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

780 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-unit inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and filed areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded filed-area range
Tower 120020000014.71–81.29 sq m≈ 158–875 sq ft
Tower 218818512036.09–81.29 sq m≈ 388–875 sq ft
Tower 319619204035.78–62.90 sq m≈ 385–677 sq ft
Tower 419619204035.64–87.18 sq m≈ 384–938 sq ft

Area means carpet area for building units and plot area for plots. Size alone does not establish use or layout. How we read and summarise the filing →

Unit Report

Is this the right
unit for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar units and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your unit in the RERA list.

The same unit number may appear in more than one building. Check both before choosing.

780 listed entries

MahaRERA · per-unit inventory · saved-file date 18 July 2026

RERA unit list, not current availability
Unit / buildingFloor in the recordFiled areaReported statusAgreement valueAssess
GBLVT10101Tower 1 / Wing NA176.58 sq m≈ 824 sq ft · RERA carpet areaSold₹7,826,832
GBLVT10102Tower 1 / Wing NA150.86 sq m≈ 547 sq ft · RERA carpet areaSold₹5,629,621
GBLVT10103Tower 1 / Wing NA150.86 sq m≈ 547 sq ft · RERA carpet areaSold₹5,923,019
GBLVT10104Tower 1 / Wing NA176.58 sq m≈ 824 sq ft · RERA carpet areaSold₹7,664,352
GBLVT10105Tower 1 / Wing NA176.58 sq m≈ 824 sq ft · RERA carpet areaSold₹6,999,698
GBLVT10106Tower 1 / Wing NA134.12 sq m≈ 367 sq ft · RERA carpet areaSold₹4,072,915
GBLVT10107Tower 1 / Wing NA134.12 sq m≈ 367 sq ft · RERA carpet areaSold₹4,072,915
GBLVT10108Tower 1 / Wing NA176.58 sq m≈ 824 sq ft · RERA carpet areaSold₹6,871,098
GBLVT10201Tower 1 / Wing NA273.39 sq m≈ 790 sq ft · RERA carpet areaSold₹6,692,303
GBLVT10202Tower 1 / Wing NA251.45 sq m≈ 554 sq ft · RERA carpet areaSold₹4,610,254
GBLVT10203Tower 1 / Wing NA251.45 sq m≈ 554 sq ft · RERA carpet areaSold₹5,629,621
GBLVT10204Tower 1 / Wing NA273.39 sq m≈ 790 sq ft · RERA carpet areaSold₹6,658,265

Read every entry in one table: Read the complete saved unit list.

Choose the unit you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹2,326,812,619 of an estimated ₹2,386,030,404 was reported as incurred (97.5%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100024616

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower 1Excavation100.0%
Tower 1Basement (if any)100.0%
Tower 1Podiums (if any) 0.0%
Tower 1Plinth100.0%
Tower 1Stilt Floor 0.0%
Tower 1Slabs of Super Structure100.0%
Tower 1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Tower 1Sanitary Fittings within the flats / premises100.0%
Tower 1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Tower 1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Tower 1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
Tower 2Excavation100.0%
Tower 2Basement (if any)100.0%
Tower 2Podiums (if any) 0.0%
Tower 2Plinth100.0%
Tower 2Stilt Floor 0.0%
Tower 2Slabs of Super Structure100.0%
Tower 2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Tower 2Sanitary Fittings within the flats / premises100.0%
Tower 2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Tower 2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Tower 2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
Tower 3Excavation100.0%
Tower 3Basement (if any)100.0%
Tower 3Podiums (if any) 0.0%
Tower 3Plinth100.0%
Tower 3Stilt Floor 0.0%
Tower 3Slabs of Super Structure100.0%
Tower 3Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Tower 3Sanitary Fittings within the flats / premises100.0%
Tower 3Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Tower 3External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Tower 3Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%
Tower 4Excavation100.0%
Tower 4Basement (if any)100.0%
Tower 4Podiums (if any) 0.0%
Tower 4Plinth100.0%
Tower 4Stilt Floor 0.0%
Tower 4Slabs of Super Structure100.0%
Tower 4Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100.0%
Tower 4Sanitary Fittings within the flats / premises100.0%
Tower 4Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100.0%
Tower 4External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100.0%
Tower 4Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100.0%

MahaRERA project filing · read 19 July 2026 · registration P52100024616

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹1,021,804,138₹0₹2,809,607,091₹3,831,411,229
Actual raised₹526,251,501₹146,111,494₹3,059,844,886₹3,783,371,045

MahaRERA project filing · read 19 July 2026 · registration P52100024616

Quarterly filing record

23 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100024616

Documents named in the filing

  • Commencement certificate · 3 listed
  • Promoter PAN · 1 listed
  • Form 1 — Architect's certificate · 5 listed
  • Form 3 — CA certificate · 5 listed
  • Form 2 — Engineer's certificate · 5 listed
  • Title / search report · 38 listed
  • Form B — Promoter declaration · 1 listed
  • Sanctioned layout plan · 1 listed
  • Sanctioned building plan · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100024616

Builder and past records

What else does the record show?

Projects registered under this company

Manjari Housing Projects LLP

9Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 2 July 2026 – 12 July 2026

Explore other registrations

Past records of sales and unsold units

  1. 26 September 2026

    10 marked unsold · 769 sold · 1 booked.

    Saved MahaRERA unit list

  2. 17 September 2026

    10 marked unsold · 769 sold · 1 booked.

    Saved MahaRERA unit list

  3. 9 September 2026

    10 marked unsold · 769 sold · 1 booked.

    Saved MahaRERA unit list

  4. 19 July 2026

    10 marked unsold · 769 sold · 1 booked.

    Saved MahaRERA unit list

These dates show when the records were saved, not when units were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, property type and price.

Project Comparison Report

Which project should you buy in?
And which unit?

Compare up to three projects. We read their plans and RERA documents, recommend units in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-unit inventory · saved-file date 18 July 2026

This is a past RERA unit list, not current availability. It does not give the date each unit was sold.

The unit-list date is based on the saved file’s details.

Filed area means carpet area for building units and plot area for plots. Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100024616 ↗
homeonpaper