The builder’s RERA record, explained

Godrej River Crest

Manjari Housing Projects LLP · P52100077127

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Godrej River Crest (P52100077127), 133 of 216 entries were marked unsold in the MahaRERA unit list read 11 September 2026.

MahaRERA · per-unit inventory · read 11 September 2026

For Godrej River Crest, ₹15,062 per sq ft of filed area is the median rate across 83 sold or booked entries with prices in the MahaRERA unit list read 11 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-unit inventory · read 11 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find units to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular unit

See its advantages, drawbacks and how it compares with other units in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended units in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹15,062/ sq ft filed area

Across 83 sold or booked entries with reported prices. The middle 80% of rates fall between ₹14,271 and ₹18,069.

MahaRERA · per-unit inventory · read 11 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its filed area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold units and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar units sell for?

Compare filed values by building, unit-number pattern and area. See which units were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

216 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-unit inventory · read 11 September 2026

Scroll sideways to see all columns.

Building names, sale status and filed areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded filed-area range
Tower 110853154083.42–181.26 sq m≈ 898–1,951 sq ft
Tower 210829079097.17–183.81 sq m≈ 1,046–1,979 sq ft

Area means carpet area for building units and plot area for plots. Size alone does not establish use or layout. How we read and summarise the filing →

Unit Report

Is this the right
unit for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar units and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your unit in the RERA list.

The same unit number may appear in more than one building. Check both before choosing.

216 listed entries

MahaRERA · per-unit inventory · read 11 September 2026

RERA unit list, not current availability
Unit / buildingFloor in the recordFiled areaReported statusAgreement valueAssess
GRCT10101Tower 1 / Wing NA183.42 sq m≈ 898 sq ft · RERA carpet areaSold₹13,233,537
GRCT10102Tower 1 / Wing NA1110.32 sq m≈ 1,187 sq ft · RERA carpet areaMarked unsoldNot stated
GRCT10103Tower 1 / Wing NA1110.09 sq m≈ 1,185 sq ft · RERA carpet areaMarked unsoldNot stated
GRCT10104Tower 1 / Wing NA1105.5 sq m≈ 1,136 sq ft · RERA carpet areaSold₹17,269,477
GRCT10201Tower 1 / Wing NA2114.19 sq m≈ 1,229 sq ft · RERA carpet areaSold₹18,022,892
GRCT10202Tower 1 / Wing NA2110.23 sq m≈ 1,187 sq ft · RERA carpet areaSold₹17,156,224
GRCT10203Tower 1 / Wing NA2110.09 sq m≈ 1,185 sq ft · RERA carpet areaSold₹20,617,174
GRCT10204Tower 1 / Wing NA2136.24 sq m≈ 1,466 sq ft · RERA carpet areaSold₹25,800,086
GRCT10301Tower 1 / Wing NA3114.19 sq m≈ 1,229 sq ft · RERA carpet areaSold₹22,379,963
GRCT10302Tower 1 / Wing NA3110.23 sq m≈ 1,187 sq ft · RERA carpet areaMarked unsoldNot stated
GRCT10303Tower 1 / Wing NA3110.09 sq m≈ 1,185 sq ft · RERA carpet areaSold₹21,388,103
GRCT10304Tower 1 / Wing NA3136.24 sq m≈ 1,466 sq ft · RERA carpet areaBooked₹26,497,579

Read every entry in one table: Read the complete saved unit list.

Choose the unit you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹34,506,196 of an estimated ₹2,531,884,818 was reported as incurred (1.4%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100077127

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower 1Excavation10.0%
Tower 1Basement (if any)0.0%
Tower 1Podiums (if any) 0.0%
Tower 1Plinth0.0%
Tower 1Stilt Floor 0.0%
Tower 1Slabs of Super Structure0.0%
Tower 1Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 1Sanitary Fittings within the flats / premises0.0%
Tower 1Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 1External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 1Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 2Excavation10.0%
Tower 2Basement (if any)0.0%
Tower 2Podiums (if any) 0.0%
Tower 2Plinth0.0%
Tower 2Stilt Floor 0.0%
Tower 2Slabs of Super Structure0.0%
Tower 2Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 2Sanitary Fittings within the flats / premises0.0%
Tower 2Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 2External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 2Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100077127

Reported deadline extensions

Revised targetReason given by the builder
15 June 2030The project is expected to start with excavation activity after having received the tree cutting NOC. However, the delay in receipt of final tree cutting NOC was significant and has impacted our construction start timelines and effectively the timeline for project completion. Post receipt of building plan in Jun’24, our project was registered on RERA in Jul’24. Upon registration, the project was launched and unit bookings were realized. However, since last one year, we had been following up with the authorities to get the final tree cutting NOC. After many follow-ups, we have received the final NOC and are now commencing to start the construction. 3. The situation remained difficult despite our best efforts to address these problems, such as our attempt to retain labour on-site. As the construction activities must be executed in a timely manner, we are optimistic that we would also be able to execute construction activities at the required pace now that the tree cutting NOC is in place. However, due to delays seen in the past as mentioned above, we are now required to update the project's completion schedule and request an extension till 15-06-2030. We intend to execute an agreement with the customer to mention the date of possession on or before 15-06-2030. Kindly process our application and grant us the extension till 15-06-2030. After careful consideration of the current circumstances and the challenges faced, we propose a revised completion timeline. We expect the project to be completed within 15-06-2030. 5. That till date, no application for extension of the project registration has ever been made or granted. The present application is the first and last application seeking extension under Section 6 of the Real Estate (Regulation and Development) Act, 2016. 6. That the present extension is sought for a period less than twelve (12) months, and the revised proposed date of completion for the project is 15-06-2030. We kindly request you to consider our application for an extension under Section 6 of MAHARERA, considering the circumstances explained above and the supporting documents provided. We assure you to expedite the project's completion and comply with all the applicable provisions of MAHARERA.

MahaRERA project filing · read 19 July 2026 · registration P52100077127

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹45,038,494₹0₹3,345,376,442₹3,390,414,936
Actual raised₹450,173,942₹92,770,943₹309,437,260₹880,628,477

MahaRERA project filing · read 19 July 2026 · registration P52100077127

Quarterly filing record

7 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100077127

Documents named in the filing

  • Commencement certificate · 4 listed
  • Promoter PAN · 2 listed
  • Occupancy / completion certificate · 1 listed
  • Form 1 — Architect's certificate · 4 listed
  • Form 3 — CA certificate · 4 listed
  • Form 2 — Engineer's certificate · 4 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 6 listed
  • Sanctioned layout plan · 2 listed
  • Sanctioned building plan · 16 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100077127

Builder and past records

What else does the record show?

Projects registered under this company

Manjari Housing Projects LLP

9Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 2 July 2026 – 12 July 2026

Explore other registrations

Past records of sales and unsold units

  1. 28 September 2026

    133 marked unsold · 82 sold · 1 booked.

    Saved MahaRERA unit list

  2. 20 September 2026

    133 marked unsold · 82 sold · 1 booked.

    Saved MahaRERA unit list

  3. 11 September 2026

    133 marked unsold · 82 sold · 1 booked.

    Saved MahaRERA unit list

  4. 19 July 2026

    128 marked unsold · 81 sold · 7 booked.

    Saved MahaRERA unit list

These dates show when the records were saved, not when units were sold. Sales may have changed since then, even if the saved counts are the same.

Project Comparison Report

Which project should you buy in?
And which unit?

Compare up to three projects. We read their plans and RERA documents, recommend units in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-unit inventory · read 11 September 2026

This is a past RERA unit list, not current availability. It does not give the date each unit was sold.

Filed area means carpet area for building units and plot area for plots. Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100077127 ↗