The builder’s RERA record, explained

Kohinoor Avantara

Intofinity Promoters Private Limited · PR1260002501984

MahaRERA · registration record · read 2 July 2026

Choose a report ↓

What does the RERA record show?

For Kohinoor Avantara (PR1260002501984), 1373 of 1373 entries were marked unsold in the MahaRERA home list dated 18 July 2026 (saved-file date).

MahaRERA · per-home inventory · saved-file date 18 July 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Inside this registered phase

How do the buildings compare in the record?

1373 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · saved-file date 18 July 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Commercial Building720072045.66–97.16 sq m≈ 491–1,046 sq ft
Inclusive Housing880088049.99 sq m≈ 538 sq ft
Tower A15400154059.63–77.00 sq m≈ 642–829 sq ft
Tower B650065063.47–88.79 sq m≈ 683–956 sq ft
Tower C5200520107.71 sq m≈ 1,159 sq ft
Tower D18800188056.91–77.28 sq m≈ 613–832 sq ft
Tower E20400204059.39 sq m≈ 639 sq ft
Tower F20400204063.47–88.79 sq m≈ 683–956 sq ft
Tower G19200192063.47–88.79 sq m≈ 683–956 sq ft
Tower H15400154059.39 sq m≈ 639 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

1373 listed entries

MahaRERA · per-home inventory · saved-file date 18 July 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
Shop-01Commercial Building20577.84 sq m≈ 838 sq ftMarked unsoldNot stated
Shop-02Commercial Building20558.97 sq m≈ 635 sq ftMarked unsoldNot stated
Shop-03Commercial Building20558.97 sq m≈ 635 sq ftMarked unsoldNot stated
Shop-04Commercial Building20551.31 sq m≈ 552 sq ftMarked unsoldNot stated
Shop-05Commercial Building20549.15 sq m≈ 529 sq ftMarked unsoldNot stated
Shop-06Commercial Building20549.15 sq m≈ 529 sq ftMarked unsoldNot stated
Shop-07Commercial Building20549.15 sq m≈ 529 sq ftMarked unsoldNot stated
Shop-08Commercial Building20597.16 sq m≈ 1,046 sq ftMarked unsoldNot stated
Shop-09Commercial Building20586.28 sq m≈ 929 sq ftMarked unsoldNot stated
Shop-10Commercial Building20556.16 sq m≈ 605 sq ftMarked unsoldNot stated
Shop-101Commercial Building177.84 sq m≈ 838 sq ftMarked unsoldNot stated
Shop-102Commercial Building158.97 sq m≈ 635 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower EExcavation0.0%
Tower EPlinth0.0%
Tower EStilt Floor 0.0%
Tower ESlabs of Super Structure0.0%
Tower EInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower ESanitary Fittings within the flats / premises0.0%
Tower EStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower EExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower EInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower FExcavation0.0%
Tower FPlinth0.0%
Tower FStilt Floor 0.0%
Tower FSlabs of Super Structure0.0%
Tower FInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower FSanitary Fittings within the flats / premises0.0%
Tower FStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower FExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower FInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower GExcavation0.0%
Tower GPodiums (if any) 0.0%
Tower GPlinth0.0%
Tower GStilt Floor 0.0%
Tower GSlabs of Super Structure0.0%
Tower GInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower GSanitary Fittings within the flats / premises0.0%
Tower GStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower GExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower GInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Commercial BuildingExcavation0.0%
Commercial BuildingPlinth0.0%
Commercial BuildingStilt Floor 0.0%
Commercial BuildingSlabs of Super Structure0.0%
Commercial BuildingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Commercial BuildingSanitary Fittings within the flats / premises0.0%
Commercial BuildingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Commercial BuildingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Commercial BuildingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Inclusive HousingExcavation0.0%
Inclusive HousingPlinth0.0%
Inclusive HousingStilt Floor 0.0%
Inclusive HousingSlabs of Super Structure0.0%
Inclusive HousingInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Inclusive HousingSanitary Fittings within the flats / premises0.0%
Inclusive HousingStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Inclusive HousingExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Inclusive HousingInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower AExcavation0.0%
Tower ABasement (if any)0.0%
Tower APodiums (if any) 0.0%
Tower APlinth0.0%
Tower AStilt Floor 0.0%
Tower ASlabs of Super Structure0.0%
Tower AInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower ASanitary Fittings within the flats / premises0.0%
Tower AStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower AExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower AInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower BExcavation0.0%
Tower BPodiums (if any) 0.0%
Tower BPlinth0.0%
Tower BStilt Floor 0.0%
Tower BSlabs of Super Structure0.0%
Tower BInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower BSanitary Fittings within the flats / premises0.0%
Tower BStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower BExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower BInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower CExcavation0.0%
Tower CPlinth0.0%
Tower CStilt Floor 0.0%
Tower CSlabs of Super Structure0.0%
Tower CInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower CSanitary Fittings within the flats / premises0.0%
Tower CStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower CExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower CInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower DExcavation0.0%
Tower DPlinth0.0%
Tower DStilt Floor 0.0%
Tower DSlabs of Super Structure0.0%
Tower DInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower DSanitary Fittings within the flats / premises0.0%
Tower DStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower DExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower DInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower HExcavation0.0%
Tower HBasement (if any)0.0%
Tower HStilt Floor 0.0%
Tower HSlabs of Super Structure0.0%
Tower HInternal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower HSanitary Fittings within the flats / premises0.0%
Tower HStaircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower HExternal plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower HInstallation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 18 July 2026 · registration PR1260002501984

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹2,250,032,827₹0₹2,253,218,950₹4,503,251,777
Actual raised₹2,708,487,383₹0₹13,511,999₹2,721,999,382

MahaRERA project filing · read 18 July 2026 · registration PR1260002501984

Quarterly filing record

1 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 18 July 2026 · registration PR1260002501984

Documents named in the filing

  • Promoter PAN · 2 listed
  • Sanctioned building plan · 84 listed
  • Form B — Promoter declaration · 2 listed
  • Commencement certificate · 3 listed
  • Sanctioned layout plan · 2 listed
  • Title / search report · 1 listed
  • Form 3 — CA certificate · 2 listed
  • Form 1 — Architect's certificate · 1 listed
  • Form 2 — Engineer's certificate · 1 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 18 July 2026 · registration PR1260002501984

Builder and past records

What else does the record show?

Projects registered under this company

Intofinity Promoters Private Limited

6Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 2 July 2026 – 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 21 September 2026

    1373 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  2. 12 September 2026

    1373 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  3. 4 September 2026

    1373 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

  4. 18 July 2026

    1373 marked unsold · 0 sold · 0 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 2 July 2026

MahaRERA · per-home inventory · saved-file date 18 July 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

The home-list date is based on the saved file’s details.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search PR1260002501984 ↗