The builder’s RERA record, explained

Kohinoor Kaleido-Phase-II

Intofinity Promoters Private Limited · P52100078107

MahaRERA · registration record · read 12 July 2026

Choose a report ↓

What does the RERA record show?

For Kohinoor Kaleido-Phase-II (P52100078107), 745 of 995 entries were marked unsold in the MahaRERA home list read 11 September 2026.

MahaRERA · per-home inventory · read 11 September 2026

For Kohinoor Kaleido-Phase-II, ₹3,657 per sq ft of carpet area is the median rate across 250 sold or booked entries with prices in the MahaRERA home list read 11 September 2026. These are historical agreement values, not current asking prices.

MahaRERA · per-home inventory · read 11 September 2026

These are past reported prices and sale statuses, not today’s quotes or availability. The details apply to this registered phase only.

What would help you decide?

Buyer’s Report

Understand this project

Find homes to consider, with advice on light, layout, privacy and surroundings.

₹4,999

Unit Report

Check a particular home

See its advantages, drawbacks and how it compares with other homes in this project.

₹3,999

Project Comparison Report

Choose between projects

Compare two or three projects and get recommended homes in order, with reasons for each choice.

From ₹7,999

Choose projects →

Project status and completion date.

Prices reported to RERA

What prices have been reported?

₹3,657/ sq ft carpet area

Across 250 sold or booked entries with reported prices. The middle 80% of rates fall between ₹3,657 and ₹12,547.

MahaRERA · per-home inventory · read 11 September 2026

How is this calculated?

For each sold or booked entry, we divide the reported agreement value by its carpet area in square feet. The median is the middle rate when these rates are put in order. We show it only when at least five entries have prices. We exclude valuations of unsold homes and government reference rates. The figures may include different sizes and property types. They are historical agreement values, not current asking prices or the total cost including extra charges.

Sales Report

What did similar homes sell for?

Compare reported agreement values by building, size and floor. See which homes were marked unsold on the date shown.

₹2,999 · delivered on payment

Inside this registered phase

How do the buildings compare in the record?

995 filed entries, grouped by their recorded building names. These entries may include homes, shops or other property types.

MahaRERA · per-home inventory · read 11 September 2026

Scroll sideways to see all columns.

Building names, sale status and carpet areas — not current availability
Filed buildingEntriesSoldBookedMarked unsoldOther / unstated statusRecorded carpet-area range
Tower 10400040019.66–83.73 sq m≈ 212–901 sq ft
Tower A7442042093.88–111.98 sq m≈ 1,011–1,205 sq ft
Tower A916600166019.66–83.73 sq m≈ 212–901 sq ft
Tower-A11176420134044.75–84.09 sq m≈ 482–905 sq ft
Tower-A12176550121044.75–84.09 sq m≈ 482–905 sq ft
Tower-A3217147070035.51–50.00 sq m≈ 382–538 sq ft
Tower-A817640172044.75–84.09 sq m≈ 482–905 sq ft

Different sizes are not necessarily different bedroom types. How we read and summarise the filing →

Unit Report

Is this the right
home for you?

Understand its light, privacy, layout and surroundings. See how it compares with similar homes and other options in this project.

₹3,999 · 1 working day

Didn’t help you decide? Full refund — no questions asked.

Find your home in the RERA list.

The same home number may appear in more than one building. Check both before choosing.

995 listed entries

MahaRERA · per-home inventory · read 11 September 2026

RERA home list, not current availability
Home / buildingFloor in the recordCarpet areaReported statusAgreement valueAssess
A10-104Tower 10163.92 sq m≈ 688 sq ftMarked unsoldNot stated
A10-105Tower 10157.47 sq m≈ 619 sq ftMarked unsoldNot stated
A10-106Tower 10183.73 sq m≈ 901 sq ftMarked unsoldNot stated
A10-204Tower 10263.92 sq m≈ 688 sq ftMarked unsoldNot stated
A10-205Tower 10257.47 sq m≈ 619 sq ftMarked unsoldNot stated
A10-206Tower 10283.73 sq m≈ 901 sq ftMarked unsoldNot stated
A10-304Tower 10363.92 sq m≈ 688 sq ftMarked unsoldNot stated
A10-305Tower 10357.47 sq m≈ 619 sq ftMarked unsoldNot stated
A10-306Tower 10383.73 sq m≈ 901 sq ftMarked unsoldNot stated
A10-404Tower 10463.92 sq m≈ 688 sq ftMarked unsoldNot stated
A10-405Tower 10457.47 sq m≈ 619 sq ftMarked unsoldNot stated
A10-406Tower 10483.73 sq m≈ 901 sq ftMarked unsoldNot stated

Read every entry in one table: Read the complete saved home list.

Choose the home you want us to assess. When preparing your report, we find it on the plans and examine its position and layout.

More from the RERA documents

Construction progress and project documents.

Cost reported as incurred

₹80,643,095 of an estimated ₹497,868,179 was reported as incurred (16.2%). This percentage is about costs. It does not show how much construction is complete.

MahaRERA project filing · read 19 July 2026 · registration P52100078107

Work reported, by building

Different activities can be at different stages. The builder reported these percentages to RERA. They do not come from a site inspection or confirm a handover date.

See all reported activities
BuildingActivityReported
Tower-A3Excavation100.0%
Tower-A3Basement (if any)100.0%
Tower-A3Podiums (if any) 0.0%
Tower-A3Plinth100.0%
Tower-A3Stilt Floor 60.0%
Tower-A3Slabs of Super Structure8.0%
Tower-A3Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises2.0%
Tower-A3Sanitary Fittings within the flats / premises0.0%
Tower-A3Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower-A3External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower-A3Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower-A8Excavation0.0%
Tower-A8Basement (if any)0.0%
Tower-A8Podiums (if any) 0.0%
Tower-A8Plinth0.0%
Tower-A8Stilt Floor 0.0%
Tower-A8Slabs of Super Structure0.0%
Tower-A8Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower-A8Sanitary Fittings within the flats / premises0.0%
Tower-A8Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower-A8External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower-A8Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower-A11Excavation0.0%
Tower-A11Basement (if any)0.0%
Tower-A11Podiums (if any) 0.0%
Tower-A11Plinth0.0%
Tower-A11Stilt Floor 0.0%
Tower-A11Slabs of Super Structure0.0%
Tower-A11Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower-A11Sanitary Fittings within the flats / premises0.0%
Tower-A11Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower-A11External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower-A11Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower-A12Excavation0.0%
Tower-A12Basement (if any)0.0%
Tower-A12Podiums (if any) 0.0%
Tower-A12Plinth0.0%
Tower-A12Stilt Floor 0.0%
Tower-A12Slabs of Super Structure0.0%
Tower-A12Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower-A12Sanitary Fittings within the flats / premises0.0%
Tower-A12Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower-A12External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower-A12Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower A7Excavation0.0%
Tower A7Basement (if any)0.0%
Tower A7Podiums (if any) 0.0%
Tower A7Plinth0.0%
Tower A7Stilt Floor 0.0%
Tower A7Slabs of Super Structure0.0%
Tower A7Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower A7Sanitary Fittings within the flats / premises0.0%
Tower A7Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower A7External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower A7Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower A9Excavation0.0%
Tower A9Basement (if any)0.0%
Tower A9Podiums (if any) 0.0%
Tower A9Plinth0.0%
Tower A9Stilt Floor 0.0%
Tower A9Slabs of Super Structure0.0%
Tower A9Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower A9Sanitary Fittings within the flats / premises0.0%
Tower A9Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower A9External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower A9Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%
Tower 10Excavation0.0%
Tower 10Basement (if any)0.0%
Tower 10Podiums (if any) 0.0%
Tower 10Plinth0.0%
Tower 10Stilt Floor 0.0%
Tower 10Slabs of Super Structure0.0%
Tower 10Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0.0%
Tower 10Sanitary Fittings within the flats / premises0.0%
Tower 10Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0.0%
Tower 10External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0.0%
Tower 10Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0.0%

MahaRERA project filing · read 19 July 2026 · registration P52100078107

Where the project funding comes from

RERA records separate the builder’s own funds, loans and payments from buyers. Money raised and the project budget are different figures.

FilingOwn fundsBorrowingPayments from buyersTotal
Estimated plan₹250,000,000₹0₹570,011,890₹820,011,890
Actual raised₹94,380,963₹0₹189,777,570₹284,158,533

MahaRERA project filing · read 19 July 2026 · registration P52100078107

Quarterly filing record

6 elapsed quarterly periods in the captured compliance schedule. No active quarterly default was recorded in this snapshot.

MahaRERA project filing · read 19 July 2026 · registration P52100078107

Documents named in the filing

  • Sanctioned building plan · 50 listed
  • Sanctioned layout plan · 45 listed
  • Form B — Promoter declaration · 1 listed
  • Title / search report · 2 listed
  • Occupancy / completion certificate · 3 listed
  • Commencement certificate · 2 listed
  • Promoter PAN · 1 listed
  • Form 2 — Engineer's certificate · 5 listed
  • Form 3 — CA certificate · 7 listed
  • Form 1 — Architect's certificate · 5 listed

A listed document does not confirm that an approval is still valid. Paid reports examine the documents themselves.

MahaRERA project filing · read 19 July 2026 · registration P52100078107

Builder and past records

What else does the record show?

Projects registered under this company

Intofinity Promoters Private Limited

6Pune registrations

These registrations use the same company name. Each phase counts separately. This is not a count of completed developments or a rating of the builder’s delivery record.

MahaRERA Pune registration records · read 2 July 2026 – 12 July 2026

Explore other registrations

Past records of sales and unsold homes

  1. 28 September 2026

    745 marked unsold · 250 sold · 0 booked.

    Saved MahaRERA home list

  2. 20 September 2026

    745 marked unsold · 250 sold · 0 booked.

    Saved MahaRERA home list

  3. 11 September 2026

    745 marked unsold · 250 sold · 0 booked.

    Saved MahaRERA home list

  4. 19 July 2026

    848 marked unsold · 147 sold · 0 booked.

    Saved MahaRERA home list

These dates show when the records were saved, not when homes were sold. Sales may have changed since then, even if the saved counts are the same.

More projects to explore

Other projects in this locality.

These projects list the same locality. They may differ in exact location, home type and price.

Project Comparison Report

Which project should you buy in?
And which home?

Compare up to three projects. We read their plans and RERA documents, recommend homes in each, and put the best choices for you in order. See the advantages and drawbacks of each choice.

Create my Comparison Report →

2 projects · ₹7,999
3 projects · ₹9,999

Within 1 working day

Didn’t help you decide? Full refund — no questions asked.

Compare project details for free →

Sources and dates.

MahaRERA · registration record · read 12 July 2026

MahaRERA · per-home inventory · read 11 September 2026

This is a past RERA home list, not current availability. It does not give the date each home was sold.

Areas are reported in square metres. Square-foot figures are rounded conversions. This free page does not calculate dimensions or facing directions from drawings.

Open MahaRERA · search P52100078107 ↗